Spot On Civil completed water main replacement works across multiple sites in Swan Hill and Kerang as part of an urban water infrastructure upgrade program.
The project involved staged pipeline construction, directional boring, property service connections, excavation, trenching, reinstatement and associated civil works completed in live community environments with a strong focus on safety, traffic management and minimising disruption to residents and surrounding infrastructure.
Works included:
- Site establishment and traffic management
- Underground service locating and service proving
- Hydro excavation works
- Directional boring for trenchless service installation
- Excavation and trenching works
- Installation of new water main infrastructure
- Property service connections
- Soil compaction and water quality testing
- Reinstatement of roads, footpaths and surrounding surfaces
- Final clean-up and as-constructed documentation
The project was delivered across multiple locations including Gray Street and Palaroo Street in Swan Hill and Burgyone Street in Kerang.
Spot On Civil utilised a structured staged delivery methodology to maintain efficiency, manage stakeholder impacts and ensure compliance with all project specifications and statutory requirements.
The Kerang component of the project was undertaken in proximity to a local school and scheduled for completion during the school holiday period to minimise impacts on traffic, pedestrians and the surrounding community.
Hydro excavation techniques were utilised where required to safely expose and protect existing underground infrastructure prior to excavation works commencing, while directional boring was used to minimise surface disruption and reduce reinstatement requirements in selected areas.
The project highlights Spot On Civil’s growing capability in water, sewer and underground civil infrastructure works across regional Victoria including trenchless installation solutions and integrated underground service delivery.
Client Testimonial
Our Swan Hill and Kerang teams and contractors have been busy completing their annual water mains replacement program, with the Swan Hill mains replacements be…Our Swan Hill and Kerang teams and contractors have been busy completing their annual water mains replacement program, with the Swan Hill mains replacements being completed in March 2026.
Burgoyne St, Kerang is also currently undergoing upgrades, with work scheduled to be completed in mid-April.
A lot of the projects we undertake would not be possible without the collaboration with local contractors. Thanks to Spot On Civil who are completing the works to help upgrade our assets.